Delhi Zone – I: Planned maintenance activity 6:30 AM-8:30AM 20 Nov 2010

The Delhi Zone – I has the following planned maintenance activity scheduled between 6:30 AM-8:30AM 20 Nov 2010.

UPS maintenance task will be carried out on Saturday 20th Nov between 6:30AM-8:30AM

While we don’t expect any downtime due the same, under extremely rare circumstances some of the machines might be rebooted when the switchover between the two redundant power supplies happens atleast twice during the activity.

Please email us at support@e2enetworks.com for any concerns regarding the activity

Update:-
Nov 20, 2010 8:41AM: The critical part of maintenance is over, there was no downtime due to it and none is expected now while the maintenance would last another 10 minutes.
Nov 20, 2010 8:50AM: The maintenance activity is over.